Abuja Light Rail Project 84% Complete, FCT Transport Secretary Says

Abuja Light Rail

The ongoing Abuja light rail project is 84.33 per cent complete and will be commission in December this year, the Acting Secretary of Federal Capital Territory’s Transport Secretariat, Alhaji AbdulHamid Suleiman, has said.

Suleiman told the News Agency of Nigeria (NAN) in Abuja on Tuesday that 45.245 kilometres double track of the rail had been completed.

The project awarded on May 25, 2007 is being handled by China Civil Engineering Construction Corporation.

He said the cost of the project was $841. 645 million with completion period of 48 months.

“This consisted of approximately 60.67 kilometers of standard gauge double railway track and associated permanent way within FCT.

“In Aug. 2012, due to deficiencies noticed in the estimations, the scope of the contract was varied to $823, 540 million for the final design and construction of Lots A1 and 3.

“The project has attained about 84. 33 per cent completion as at Dec. 2016’’, he said.

The acting secretary stressed that the total length of double tracks of 45.245 kilometres has reached 98 per cent completion.

Suleiman said 12 stations had reached 75 per cent completion, 50 culverts 100 per cent completion, nine pedestrian overpasses had also reached 85 per cent completion.

He said 13 railway bridges were 100 per cent completed, 15 flyover bridges 80 per cent completed, locomotive and rolling stone stock depot also reached 85 per cent completion, communication 67 per cent and signaling at 87 percent completion.

Suleiman said: “The projected date for the completion of the project is Dec. 2017.

“The feasibility study and conceptual design for the remaining lots 4, 5 and 6 are under procurement.

“These lots are available for concession under a Design, Build and Operate basis,’’ he said.

Source: NAN